Replacement of Two (2) Trane Centrifugal Chillers & Two RTUs

Location: Georgia State Bar Association, Atlanta GA
Equipment: Replacement of Two (2) Trane Centrifugal Chillers & Two RTUs

Description of Job: Though a competitive bid process; Galgon HVAC was selected to perform this replacement. The project required coordination with the City of Atlanta; through this we were able to put together a schedule for an execution date. The replacement of two existing chillers and two existing RTUs were scheduled for a Saturday and required street closures.

Due to this fact we knew we had to be fully prepared for “lift day”. In the weeks leading up; the team was selected from our company to execute this project and to discuss strategy. Decommissioning of the existing equipment took place the week before and when “lift day” arrived we were ready to execute with no delays. The two chillers were removed through the roof and the new equipment was installed. The two RTUs, which serve the elevator equipment rooms, were replaced and up and running the same day.

The job was completed on the scheduled Saturday; with the piping of the two chillers taking place the following week. Galgon HVAC’s pipefitters/welders took pride with every pipe they fitted and weld they made. With the care and precision of our technicians the two chillers were started and running on the following week.